Paving Notice – Bush Street – Old Main St. to Shaws Creek Rd.

October 25th, 2024

Milling, Base Repairs and Paving Notice on Bush St

Belfountain Rehabilitation and Corridor Improvements, Town of Caledon, Project 14-4065

This notice provides an update to the Belfountain Community regarding paving works on the Project 14-4065: Belfountain Rehabilitation and Improvements, Town of Caledon.

Peel’s contractor (Four Seasons Site Development Ltd.) has schedule milling, base repairs and paving works on Bush St (from Old Main St to Shaws Creek Rd) the week of October 28th 2024.

The schedule for paving works on Old Main St are tentative and subject to weather. In the event of rain or unforeseen circumstances the works maybe delayed. 

Activity

Start Date

Anticipated Duration

Milling and Base Repairs

Thursday, October 31st,2024

1 Day

Paving Friday, November 1st, 2024 1 Day
     

 What to expect:

  •  We will maintain a single of traffic at all times, however, motorists should expect delays in travel as the operation is underway. Emergency access will be maintained at all times.
  • During paving operations your driveway may temporarily be blocked as the machinery passes through the corridor. This will be temporary and short duration, however if you require immediate access in and out of your driveway during the operation – the paving crew and our site representatives will be there to assist you.

Who can I contact?

 

Name

Title

Organization

Contact Information

Ommar Moeen

Project Manager

Region of Peel

905-791-7800 ext. 7998

ommar.moeen@peelregion.ca

construction@peelregion.ca

Ole Petersen

Construction Inspector

Region of Peel

905-791-7800 ext. 3246

ole.petersen@peelregion.ca

 

 

 

24/7 (Project Related Emergency/After Hours) #: 905-791-7800

 

This entry was posted in Events. Bookmark the permalink.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.